NEW PRODUCTION FACILITY FOR GULF NEWS
ASIA was awarded the enabling works for this project. The scope consists of comprehensive works and services such as site clearance, site leveling and ground improvements works. The ground improvement was done using the techniques of Dynamic Compaction and Dynamic Replacements. The enabling works covered an area of 54,983 Sqm of the 86,000 Sqm plot area.
- Client : M/s Al Nisr Publishing (Gulf News) L.L.C.
- Project Manager : M/s Faithful + Gould.
- Consultant : M/s WS Atkins and Partners Overseas.
- Location : Dubai Investment Park (DIP) on Plot No. 597-654, Dubai, U.A.E.
- Duration : 85 Days.
- Built-Up Area : 54,983 Sqm.
- Scope : Enabling Works.